Sr. No Project Capacity (MW) ESTIMATED COST M. Rs M.US$ Status
1. Nagdar (Neelum) 35.00 11786.00 63.00 • PC-I submitted
Outsource funding is under process with EAD.
2. Dowarian (Neelum) 40.00 12028.00 72.00 • PC-I submitted
Outsource funding is under process with EAD.
3. Riali-I HPP (Muzaffarabad) 4.0 1768.00 8.0 Feasibility study completed.
4. Nauseri Diversion 48.00 21216.00 96.00 Feasibility study in process with WAPDA.
5. Kahori-Dhani (Muzaffarabad) 30.0 13260.00 60.0 Feasibility study in process.
6. Batdara (Muzaffarabad) 5.0 2210.00 10.00 Feasibility study completed.
7. Sharda-II (Neelum Valley) 30.0 13260.00 60.00 Feasibility study completed.
8. Bheri HPP (Muzaffarabad) 6.0 2652.00 12.00 Feasibility study completed.
Total 198 78108.00